Advance payment
Payment is the transfer between parties of some form of value (such as funds, services, assets) in an agreed exchange. This can be for goods, services or to fulfil a legal obligation such as a debt. The most common form of payment involves money although it can also take the form of other benefits, and is typically preceded by a bill or invoice specifying the amount due.
An advance payment, sometimes referred to as a down payment, or ex gratis payment, is when part of a contractual sum is paid in advance of the exchange, i.e. before any work has been done or goods supplied. Advance payments are typically recorded as prepaid expenses by the payer and recorded as assets on the balance sheet.
On a construction project, a contractor may request an advance payment to help them meet significant start up or procurement costs that may have to be incurred before construction begins. For example, where they have had to purchase high-value plant, equipment or materials specifically for the project. In these instances, the client should require an advanced payment bond. This secures the payment against default by the contractor.
For more information, see Advance payment bond.
It is also sometimes necessary for the client to pay for items even though they remain ‘off-site’, for example, where a contractor has made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme. However, this does put the client at risk, for example if the contractor or supplier becomes insolvent and the items are then not delivered, even though payment has been made.
Several mechanisms are available to protect the client, however, none of these is fool proof. Judgement is necessary to assess the risk to the project, or the potential loss to the client versus the benefit of greater certainty of supply.
For example, a ‘vesting certificate’ or ‘certificate of vesting’ may be required from the contractor (or sub-contractors or suppliers), certifying that ownership of goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).
For more information see: Off site materials.
[edit] Related articles on Designing Buildings
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.