Advance payment
Payment is the transfer between parties of some form of value (such as funds, services, assets) in an agreed exchange. This can be for goods, services or to fulfil a legal obligation such as a debt. The most common form of payment involves money although it can also take the form of other benefits, and is typically preceded by a bill or invoice specifying the amount due.
An advance payment, sometimes referred to as a down payment, or ex gratis payment, is when part of a contractual sum is paid in advance of the exchange, i.e. before any work has been done or goods supplied. Advance payments are typically recorded as prepaid expenses by the payer and recorded as assets on the balance sheet.
On a construction project, a contractor may request an advance payment to help them meet significant start up or procurement costs that may have to be incurred before construction begins. For example, where they have had to purchase high-value plant, equipment or materials specifically for the project. In these instances, the client should require an advanced payment bond. This secures the payment against default by the contractor.
For more information, see Advance payment bond.
It is also sometimes necessary for the client to pay for items even though they remain ‘off-site’, for example, where a contractor has made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme. However, this does put the client at risk, for example if the contractor or supplier becomes insolvent and the items are then not delivered, even though payment has been made.
Several mechanisms are available to protect the client, however, none of these is fool proof. Judgement is necessary to assess the risk to the project, or the potential loss to the client versus the benefit of greater certainty of supply.
For example, a ‘vesting certificate’ or ‘certificate of vesting’ may be required from the contractor (or sub-contractors or suppliers), certifying that ownership of goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).
For more information see: Off site materials.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Updated supplier guide can help electrical contractors engage with NHP.
CIAT confirm the winners of the 2026 architectural technology awards.
Government launches a one stop shop for flood preparedness.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.
Undervaluing our industrial past
Heritage value changes as taste for building styles changes.
Changing expectations around competence and compliance
New information sheet from CIAT.
Grenfell investigation files passed to CPS
Angela Rayner apologises on behalf of the British state.